R1 | No Network Architect is available for the next month | Network design cannot commence without an architect, which will delay project start | Jim | High | Medium | 2 | Mitigate | The Network Engineer can begin preliminary design. Network Architect can review periodically for general feedback | | | Assumes the Network Architect can find small blocks of time to do high level review. | | | | Accept | |
R2 | Building construction could be delayed, pushing back our start date | If the delay is long, team members might get assigned to other projects. | Jim | Medium | Medium | 3 | Transfer | Include a clause in the contract stipulating that Blue Suit will pay for staff time beginning on the planned start date, even if work cannot commence. | | | Assuming we decided on a DJ as the music provider instead of a band. | | | | Transfer | |